2026 Licensing & Certification Curricula (Securities, Cloud, IT, Real Estate, Bar & CPA) are now live
OpenExamHub ยท Source-Cited Licensing Prep2026 Examination Standards

PMI PMPยฎ Exam-Day Cheat Sheet & Formula Guide

High-yield Earned Value Management formulas, conflict resolution strategies, agile ceremonies, risk matrices, and contract calculation tables for the PMI PMPยฎ certification examination. Review these essential tables before entering the test center.

๐Ÿ“Œ Quick Summary / Core Test Principles:PMP Quick Rules: EVM: CV = EV - AC, SV = EV - PV, CPI = EV / AC, SPI = EV / PV; EAC = BAC / CPI (typical); TCPI = (BAC - EV) / (BAC - AC); Conflict: Collaborating (Win-Win, root cause) preferred; Compromising (lose-lose); Forcing only for crises/safety; Risks: Threats (Escalate, Avoid, Transfer, Mitigate, Accept); Opportunities (Escalate, Exploit, Share, Enhance, Accept); Contracts: FFP (buyer risk minimum), CPFF/CPIF (buyer risk maximum), PTA = ((Ceiling Price - Target Price) / Buyer Share Ratio) + Target Cost; Change Control: Submit -> Evaluate impact -> CR -> CCB review -> Update plan/baselines -> Inform.
Mathematical Calculations

Earned Value Management (EVM) Master Formula Sheet

Metric / AcronymMathematical FormulaInterpretation BenchmarkPMP Exam Trap / Rule
Cost Variance (CV)CV = EV - AC> 0: Under budget (favorable) = 0: Exactly on budget < 0: Over budget (unfavorable)Always subtract AC from EV. Negative is bad (over budget).
Schedule Variance (SV)SV = EV - PV> 0: Ahead of schedule (favorable) = 0: On schedule < 0: Behind schedule (unfavorable)Always subtract PV from EV. Negative is bad (behind schedule).
Cost Performance Index (CPI)CPI = EV / AC> 1.0: Earning more value than cost = 1.0: Target baseline < 1.0: Cost overrun (e.g. 0.80 = $0.80 value per $1 spent)CPI is the single most reliable predictor of final project cost performance.
Schedule Performance Index (SPI)SPI = EV / PV> 1.0: Progressing faster than planned = 1.0: On schedule < 1.0: Progressing slower than plannedSPI converges toward 1.0 at project completion even if the project is late.
Estimate at Completion (EAC) - TypicalEAC = BAC / CPIUsed when current cost performance is expected to continue indefinitely.Default formula when question states 'variances are expected to continue'.
Estimate at Completion (EAC) - AtypicalEAC = AC + (BAC - EV)Used when past anomalies are not expected to recur in future work.Assumes remaining work will be completed at the originally planned budget rate.
Estimate to Complete (ETC)ETC = EAC - ACHow much additional money is required to finish the project.Does not include money already spent (AC).
Variance at Completion (VAC)VAC = BAC - EAC> 0: Under original budget < 0: Over original budgetNegative VAC indicates projected cost overrun at completion.
To-Complete Performance Index (TCPI) - BACTCPI = (BAC - EV) / (BAC - AC)> 1.0: Harder to achieve (need higher efficiency) < 1.0: Easier to achieveTCPI > 1.10 is generally considered unfeasible; negotiate an updated EAC.
๐Ÿ’ก Pro Tip:Memory Rule: Every variance formula starts with EV (EV - AC, EV - PV). Every index formula starts with EV on top (EV / AC, EV / PV). Above 1.0 or positive is good; below 1.0 or negative is bad!
People & Interpersonal

Conflict Management Strategies (Thomas-Kilmann Model)

TechniqueApproach & DynamicsOutcome & Trade-offAppropriate Exam Context
Collaborating / Problem SolvingIncorporate multiple viewpoints; explore objective data to find an optimal solution.Win-Win; produces lasting consensus and high commitment.Preferred PMI approach for technical and architectural disagreements when time permits.
Compromising / ReconcilingSearch for solutions that bring some degree of satisfaction to all parties; split the difference.Lose-Lose (partial win/loss); neither party gets everything.Used when time is constrained or parties have equal power with mutually exclusive goals.
Forcing / DirectingPush one's viewpoint at the expense of others; exercise positional authority.Win-Lose; damages team morale and psychological safety.Strictly appropriate during emergencies, safety hazards, life-critical issues, or mandatory compliance.
Smoothing / AccommodatingEmphasize areas of agreement rather than areas of difference; maintain harmony.Temporary fix; root cause remains unaddressed.Used to calm emotions temporarily so pressing immediate work can proceed.
Withdrawing / AvoidingRetreat from an actual or potential conflict situation; postpone issue to be better prepared.No resolution; problem inevitably resurfaces.Appropriate only when issue is trivial, emotions are explosive, or to cool down temporarily.
๐Ÿ’ก Pro Tip:On the PMP exam, Collaborating / Problem Solving is the correct answer ~80% of the time. Forcing is correct ONLY when safety, ethics, or legal non-compliance is at stake.
Risk Management

Risk Response Strategies: Threats vs. Opportunities

Strategy TypeThreat Strategy (Negative)Opportunity Strategy (Positive)Key PMP Distinction
Eliminate / GuaranteeAvoid: Change project management plan to eliminate threat entirely (e.g. cancel feature, change tech).Exploit: Eliminate uncertainty to ensure the opportunity 100% definitely happens (e.g. assign top talent).Avoidance eliminates 100% of the threat; Exploit guarantees 100% of the opportunity.
Shift / PartnerTransfer: Shift ownership/financial impact to a third party (e.g. insurance, warranties, fixed-price subcontracts).Share: Allocate ownership to a third party best able to capture the benefit (e.g. joint venture, revenue share).Transfer shifts liability/threat; Share divides mutual reward/upside with partners.
Adjust Prob / ImpactMitigate: Take early action to reduce probability and/or impact (e.g. prototypes, redundancies, testing).Enhance: Take action to increase probability and/or positive impact (e.g. add extra marketing, fast compute).Mitigation reduces negative downside; Enhancement magnifies positive upside.
AcknowledgeAccept (Passive or Active): Acknowledge risk; take no action except establishing a contingency reserve if active.Accept: Acknowledge opportunity; take advantage if it occurs naturally without active investment.Passive acceptance requires no action; Active acceptance establishes contingency reserves.
Boundary ThresholdEscalate: Threat exceeds project manager authority or affects program/portfolio; pass to sponsor/PMO.Escalate: Opportunity exceeds project boundary or benefits multiple enterprise units; pass to executive sponsor.Once escalated, the risk is no longer managed in the project risk register by the PM.
๐Ÿ’ก Pro Tip:If you hire a contractor under Fixed Price to handle a risky module, that is Risk Transfer. If you write automated unit tests to catch defects early, that is Risk Mitigation.
Procurement Management

Contract Types & Risk Allocation Matrix

Contract TypeCost Risk BearerScope Definition RequirementIdeal Project Context
Firm Fixed Price (FFP)Seller (Highest seller risk, lowest buyer risk)Scope must be 100% completely defined, detailed, and unambiguous.Standard commercial off-the-shelf purchases or well-understood construction.
Fixed Price Incentive Fee (FPIF)Shared up to Ceiling; Seller assumes 100% above Point of Total Assumption (PTA).Well-defined with specific quantitative performance/cost incentives.Manufacturing or aerospace where cost control incentives align buyer and seller.
Cost Plus Fixed Fee (CPFF)Buyer (Buyer reimburses all legitimate costs + set fee)Scope is uncertain, exploratory, or involves significant R&D.Cutting-edge research, novel software engineering, or emergency disaster response.
Cost Plus Incentive Fee (CPIF)Shared (Cost overruns/underruns shared according to predetermined ratio, e.g. 80/20).Uncertain scope where target costs and sharing ratios motivate efficiency.Complex enterprise transformation programs spanning multiple years.
Time and Materials (T&M)Buyer (Buyer pays set hourly rate for all time spent)Scope is undefined, emergent, or staff augmentation is needed quickly.Emergency expert troubleshooting or temporary contractor augmentation; ALWAYS require a Not-to-Exceed (NTE) cap.
๐Ÿ’ก Pro Tip:Formula to know: Point of Total Assumption (PTA) = ((Ceiling Price - Target Price) / Buyer Share Ratio) + Target Cost. Beyond PTA, the seller absorbs every dollar of cost overrun.
Agile Frameworks

Agile Ceremonies, Roles & Artifacts Quick-Reference

Ceremony / Role / ArtifactPrimary OwnerCore Purpose & TimeboxKey Exam Insight
Product Owner (PO)Individual (Single voice of customer)Owns product vision, manages and prioritizes the Product Backlog, accepts/rejects user stories.Only the Product Owner can cancel a sprint or accept completed user stories.
Scrum Master / Agile CoachServant LeaderRemoves impediments, facilitates ceremonies, shields team from distractions, coaches agile mindset.The Scrum Master NEVER directs work, assigns tasks, or makes technical choices for the team.
Development TeamCross-Functional, Self-OrganizingEstimates stories, decomposes tasks, creates the increment, owns the 'How', maintains quality.The team collectively decides how many story points to pull into a sprint based on velocity.
Sprint PlanningEntire Scrum TeamTimebox: 8h for 4-week sprint (2h/week). Selects Product Backlog items, crafts Sprint Goal, creates Sprint Backlog.The Sprint Goal must not be modified once sprint planning concludes.
Daily StandupDevelopment TeamTimebox: 15 minutes. Daily synchronization: What did I do? What will I do? What impediments block me?Not a management status report meeting; it is a peer synchronization for developers.
Sprint ReviewScrum Team + StakeholdersTimebox: 4h for 4-week sprint (1h/week). Live demonstration of working software increment; gathers feedback.Focuses on product increment inspection; not a PowerPoint slide presentation.
Sprint RetrospectiveScrum Team onlyTimebox: 3h for 4-week sprint (45m/week). Inspect and adapt the team process, tooling, relationships, and Definition of Done.Top improvement action items must be prioritized and added directly into the next sprint backlog.
๐Ÿ’ก Pro Tip:Do not confuse Definition of Ready (DoR: criteria a story must meet before entering sprint) with Definition of Done (DoD: quality criteria a story must satisfy to be deemed shippable).
Process Governance

Integrated Change Control & Decision Sequence

Step NumberGovernance ActionResponsible RolePMI Mindset Rationale
Step 1: Prevent & EducateInfluence factors that circumvent change control; educate stakeholders on project governance.Project ManagerProactively prevent unauthorized scope creep before it starts.
Step 2: Formal RequestEnsure the change is formally submitted and documented in the Change Log.Requester / Project ManagerVerbal change requests are never implemented without formal documentation.
Step 3: Comprehensive Impact AssessmentAnalyze impact across ALL project constraints: scope, schedule, cost, quality, risk, resources, customer satisfaction.Project Manager & TeamNever say 'yes' or 'no' before thoroughly analyzing the full cross-functional impact.
Step 4: Explore AlternativesIdentify trade-offs, options, or cost-neutral adjustments to satisfy the stakeholder's underlying business need.Project ManagerDemonstrate problem-solving value rather than rigid bureaucratic refusal.
Step 5: CCB SubmissionPresent the change request, comprehensive impact analysis, and alternatives to the Change Control Board (CCB).Project ManagerBaseline changes exceed PM authority; the CCB approves, defers, or rejects.
Step 6: Baseline & Plan UpdatesIf approved, update the Project Management Plan, scope/schedule/cost baselines, and communication registers.Project ManagerNever begin physical execution until management plans and baselines are officially updated.
Step 7: Communication & ExecutionNotify all affected stakeholders of the CCB decision and execute the approved change through the team.Project Manager & TeamEnsure transparency across governance bodies and delivery teams.
๐Ÿ’ก Pro Tip:The classic PMI sequence: When a stakeholder requests a change -> 1) Document it -> 2) Assess the impact across all constraints -> 3) Submit to CCB -> 4) Update the plan upon approval -> 5) Execute!