2026 Licensing & Certification Curricula (Securities, Cloud, IT, Real Estate, Bar & CPA) are now live
OpenExamHub · Source-Cited Licensing Prep2026 Examination Standards

PMI PMP® Exam-Day Cheat Sheet & Formula Guide

High-yield Earned Value Management formulas, conflict resolution strategies, agile ceremonies, risk matrices, and contract calculation tables for the PMI PMP® certification examination. Review these essential tables before entering the test center.

📌 Quick Summary / Core Test Principles:PMP Quick Rules: EVM: CV = EV - AC, SV = EV - PV, CPI = EV / AC, SPI = EV / PV; EAC = BAC / CPI (typical); TCPI = (BAC - EV) / (BAC - AC); Conflict: Collaborating (Win-Win, root cause) preferred; Compromising (lose-lose); Forcing only for crises/safety; Risks: Threats (Escalate, Avoid, Transfer, Mitigate, Accept); Opportunities (Escalate, Exploit, Share, Enhance, Accept); Contracts: FFP (buyer risk minimum), CPFF/CPIF (buyer risk maximum), PTA = ((Ceiling Price - Target Price) / Buyer Share Ratio) + Target Cost; Change Control: Submit -> Evaluate impact -> CR -> CCB review -> Update plan/baselines -> Inform.
Mathematical Calculations

Earned Value Management (EVM) Master Formula Sheet

Metric / AcronymMathematical FormulaInterpretation BenchmarkPMP Exam Trap / Rule
Cost Variance (CV)CV = EV - AC> 0: Under budget (favorable) = 0: Exactly on budget < 0: Over budget (unfavorable)Always subtract AC from EV. Negative is bad (over budget).
Schedule Variance (SV)SV = EV - PV> 0: Ahead of schedule (favorable) = 0: On schedule < 0: Behind schedule (unfavorable)Always subtract PV from EV. Negative is bad (behind schedule).
Cost Performance Index (CPI)CPI = EV / AC> 1.0: Earning more value than cost = 1.0: Target baseline < 1.0: Cost overrun (e.g. 0.80 = $0.80 value per $1 spent)CPI is the single most reliable predictor of final project cost performance.
Schedule Performance Index (SPI)SPI = EV / PV> 1.0: Progressing faster than planned = 1.0: On schedule < 1.0: Progressing slower than plannedSPI converges toward 1.0 at project completion even if the project is late.
Estimate at Completion (EAC) - TypicalEAC = BAC / CPIUsed when current cost performance is expected to continue indefinitely.Default formula when question states 'variances are expected to continue'.
Estimate at Completion (EAC) - AtypicalEAC = AC + (BAC - EV)Used when past anomalies are not expected to recur in future work.Assumes remaining work will be completed at the originally planned budget rate.
Estimate to Complete (ETC)ETC = EAC - ACHow much additional money is required to finish the project.Does not include money already spent (AC).
Variance at Completion (VAC)VAC = BAC - EAC> 0: Under original budget < 0: Over original budgetNegative VAC indicates projected cost overrun at completion.
To-Complete Performance Index (TCPI) - BACTCPI = (BAC - EV) / (BAC - AC)> 1.0: Harder to achieve (need higher efficiency) < 1.0: Easier to achieveTCPI > 1.10 is generally considered unfeasible; negotiate an updated EAC.
💡 Pro Tip:Memory Rule: Every variance formula starts with EV (EV - AC, EV - PV). Every index formula starts with EV on top (EV / AC, EV / PV). Above 1.0 or positive is good; below 1.0 or negative is bad!
People & Interpersonal

Conflict Management Strategies (Thomas-Kilmann Model)

TechniqueApproach & DynamicsOutcome & Trade-offAppropriate Exam Context
Collaborating / Problem SolvingIncorporate multiple viewpoints; explore objective data to find an optimal solution.Win-Win; produces lasting consensus and high commitment.Preferred PMI approach for technical and architectural disagreements when time permits.
Compromising / ReconcilingSearch for solutions that bring some degree of satisfaction to all parties; split the difference.Lose-Lose (partial win/loss); neither party gets everything.Used when time is constrained or parties have equal power with mutually exclusive goals.
Forcing / DirectingPush one's viewpoint at the expense of others; exercise positional authority.Win-Lose; damages team morale and psychological safety.Strictly appropriate during emergencies, safety hazards, life-critical issues, or mandatory compliance.
Smoothing / AccommodatingEmphasize areas of agreement rather than areas of difference; maintain harmony.Temporary fix; root cause remains unaddressed.Used to calm emotions temporarily so pressing immediate work can proceed.
Withdrawing / AvoidingRetreat from an actual or potential conflict situation; postpone issue to be better prepared.No resolution; problem inevitably resurfaces.Appropriate only when issue is trivial, emotions are explosive, or to cool down temporarily.
💡 Pro Tip:On the PMP exam, Collaborating / Problem Solving is the correct answer ~80% of the time. Forcing is correct ONLY when safety, ethics, or legal non-compliance is at stake.
Risk Management

Risk Response Strategies: Threats vs. Opportunities

Strategy TypeThreat Strategy (Negative)Opportunity Strategy (Positive)Key PMP Distinction
Eliminate / GuaranteeAvoid: Change project management plan to eliminate threat entirely (e.g. cancel feature, change tech).Exploit: Eliminate uncertainty to ensure the opportunity 100% definitely happens (e.g. assign top talent).Avoidance eliminates 100% of the threat; Exploit guarantees 100% of the opportunity.
Shift / PartnerTransfer: Shift ownership/financial impact to a third party (e.g. insurance, warranties, fixed-price subcontracts).Share: Allocate ownership to a third party best able to capture the benefit (e.g. joint venture, revenue share).Transfer shifts liability/threat; Share divides mutual reward/upside with partners.
Adjust Prob / ImpactMitigate: Take early action to reduce probability and/or impact (e.g. prototypes, redundancies, testing).Enhance: Take action to increase probability and/or positive impact (e.g. add extra marketing, fast compute).Mitigation reduces negative downside; Enhancement magnifies positive upside.
AcknowledgeAccept (Passive or Active): Acknowledge risk; take no action except establishing a contingency reserve if active.Accept: Acknowledge opportunity; take advantage if it occurs naturally without active investment.Passive acceptance requires no action; Active acceptance establishes contingency reserves.
Boundary ThresholdEscalate: Threat exceeds project manager authority or affects program/portfolio; pass to sponsor/PMO.Escalate: Opportunity exceeds project boundary or benefits multiple enterprise units; pass to executive sponsor.Once escalated, the risk is no longer managed in the project risk register by the PM.
💡 Pro Tip:If you hire a contractor under Fixed Price to handle a risky module, that is Risk Transfer. If you write automated unit tests to catch defects early, that is Risk Mitigation.
Procurement Management

Contract Types & Risk Allocation Matrix

Contract TypeCost Risk BearerScope Definition RequirementIdeal Project Context
Firm Fixed Price (FFP)Seller (Highest seller risk, lowest buyer risk)Scope must be 100% completely defined, detailed, and unambiguous.Standard commercial off-the-shelf purchases or well-understood construction.
Fixed Price Incentive Fee (FPIF)Shared up to Ceiling; Seller assumes 100% above Point of Total Assumption (PTA).Well-defined with specific quantitative performance/cost incentives.Manufacturing or aerospace where cost control incentives align buyer and seller.
Cost Plus Fixed Fee (CPFF)Buyer (Buyer reimburses all legitimate costs + set fee)Scope is uncertain, exploratory, or involves significant R&D.Cutting-edge research, novel software engineering, or emergency disaster response.
Cost Plus Incentive Fee (CPIF)Shared (Cost overruns/underruns shared according to predetermined ratio, e.g. 80/20).Uncertain scope where target costs and sharing ratios motivate efficiency.Complex enterprise transformation programs spanning multiple years.
Time and Materials (T&M)Buyer (Buyer pays set hourly rate for all time spent)Scope is undefined, emergent, or staff augmentation is needed quickly.Emergency expert troubleshooting or temporary contractor augmentation; ALWAYS require a Not-to-Exceed (NTE) cap.
💡 Pro Tip:Formula to know: Point of Total Assumption (PTA) = ((Ceiling Price - Target Price) / Buyer Share Ratio) + Target Cost. Beyond PTA, the seller absorbs every dollar of cost overrun.
Agile Frameworks

Agile Ceremonies, Roles & Artifacts Quick-Reference

Ceremony / Role / ArtifactPrimary OwnerCore Purpose & TimeboxKey Exam Insight
Product Owner (PO)Individual (Single voice of customer)Owns product vision, manages and prioritizes the Product Backlog, accepts/rejects user stories.Only the Product Owner can cancel a sprint or accept completed user stories.
Scrum Master / Agile CoachServant LeaderRemoves impediments, facilitates ceremonies, shields team from distractions, coaches agile mindset.The Scrum Master NEVER directs work, assigns tasks, or makes technical choices for the team.
Development TeamCross-Functional, Self-OrganizingEstimates stories, decomposes tasks, creates the increment, owns the 'How', maintains quality.The team collectively decides how many story points to pull into a sprint based on velocity.
Sprint PlanningEntire Scrum TeamTimebox: 8h for 4-week sprint (2h/week). Selects Product Backlog items, crafts Sprint Goal, creates Sprint Backlog.The Sprint Goal must not be modified once sprint planning concludes.
Daily StandupDevelopment TeamTimebox: 15 minutes. Daily synchronization: What did I do? What will I do? What impediments block me?Not a management status report meeting; it is a peer synchronization for developers.
Sprint ReviewScrum Team + StakeholdersTimebox: 4h for 4-week sprint (1h/week). Live demonstration of working software increment; gathers feedback.Focuses on product increment inspection; not a PowerPoint slide presentation.
Sprint RetrospectiveScrum Team onlyTimebox: 3h for 4-week sprint (45m/week). Inspect and adapt the team process, tooling, relationships, and Definition of Done.Top improvement action items must be prioritized and added directly into the next sprint backlog.
💡 Pro Tip:Do not confuse Definition of Ready (DoR: criteria a story must meet before entering sprint) with Definition of Done (DoD: quality criteria a story must satisfy to be deemed shippable).
Process Governance

Integrated Change Control & Decision Sequence

Step NumberGovernance ActionResponsible RolePMI Mindset Rationale
Step 1: Prevent & EducateInfluence factors that circumvent change control; educate stakeholders on project governance.Project ManagerProactively prevent unauthorized scope creep before it starts.
Step 2: Formal RequestEnsure the change is formally submitted and documented in the Change Log.Requester / Project ManagerVerbal change requests are never implemented without formal documentation.
Step 3: Comprehensive Impact AssessmentAnalyze impact across ALL project constraints: scope, schedule, cost, quality, risk, resources, customer satisfaction.Project Manager & TeamNever say 'yes' or 'no' before thoroughly analyzing the full cross-functional impact.
Step 4: Explore AlternativesIdentify trade-offs, options, or cost-neutral adjustments to satisfy the stakeholder's underlying business need.Project ManagerDemonstrate problem-solving value rather than rigid bureaucratic refusal.
Step 5: CCB SubmissionPresent the change request, comprehensive impact analysis, and alternatives to the Change Control Board (CCB).Project ManagerBaseline changes exceed PM authority; the CCB approves, defers, or rejects.
Step 6: Baseline & Plan UpdatesIf approved, update the Project Management Plan, scope/schedule/cost baselines, and communication registers.Project ManagerNever begin physical execution until management plans and baselines are officially updated.
Step 7: Communication & ExecutionNotify all affected stakeholders of the CCB decision and execute the approved change through the team.Project Manager & TeamEnsure transparency across governance bodies and delivery teams.
💡 Pro Tip:The classic PMI sequence: When a stakeholder requests a change -> 1) Document it -> 2) Assess the impact across all constraints -> 3) Submit to CCB -> 4) Update the plan upon approval -> 5) Execute!